Works

Nicholson Road Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email [email protected] or call 9326 3666. 


Site works (ongoing)

Delivery of materials to site, earth works, drainage and relocation of underground services.

Trucks and water carts will access the site via Tulloch Way and Canna Drive, Canning Vale.

Some carpentry and steel work will take place at the Station building site, during night shifts, Monday to Friday. There will be early starts, Monday to Friday from 5:45am. 

Construction work will take place during May weekends, while trains are not operating.


Station entryway works 

From 7am to 5pm, Saturday 17 May, there will be traffic management including a reduced speed limit on Tulloch Way, adjacent to the Nicholson Road Station entry. This is to allow for the safe construction of the station entryway.

Access to driveways and properties will be maintained.

Ranford Road Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email [email protected] or call 9326 3666.   




 

Thornlie Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts.

For questions about project works, please email [email protected] or call 9326 3666.


Station work

Construction is underway to make Thornlie Station a through station, including removal of some redundant sections of the existing station. 


Out-of-hours works

From Monday 12 May until Wednesday 21 May from 5:30pm to 6am, the team will be working each night to reinstate the western carpark. This will involve concreting, asphalting, line marking and signage installation.


Wall construction, Spring Road Reserve, Thornlie

Wall construction, involving piling and lifting and placing pre-cast concrete panels will take place in May at times when trains are not operating.

At times there will be traffic management in place to create a safe working area. Access to private properties will be maintained at all times.


Out-of-Hours works for rail adjustments - Jandakot, Thornlie and Kenwick 

During May and early June, the newly installed rail network will be tested and adjusted between 6pm and 6am nightly. This will involve surveying, tamping and regulating the track, installing Overhead Line Equipment, and using specialised signalling and communications equipment.


Temporary closure of Spring Road Reserve

The Spring Road Reserve is temporarily closed to support construction until the end of the Thornlie-Cockburn Link project. Please use Banksia Circle Reserve instead. 


Rail access relocation, O'Dell Street, Thornlie

The existing rail access point on O’Dell Street will be relocated further along O’Dell Street, approximately 80 meters south-east.

Works are underway to relocate the access point including locating underground services, clearing vegetation and concreting.


Reinstatement of O'Dell Street and Spring Road Reserve, Thornlie 

Works are underway to reinstate O’Dell Street and Spring Road Reserve which includes reinstating the kerb and path, concreting and revegetation. 

Rail Corridor

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am. 

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts.

For questions about project works, please email [email protected] or call 9326 3666.


Testing and commissioning

Until mid-May, testing and commissioning will be taking place, alongside driver familiarisation. Trains will be operating along the line, in preparation for entry into revenue service.  


Building rail infrastructure

Works within the Mandurah Line rail corridor (along Kwinana Freeway) between Roe Highway and Russell Road/Gibbs Road, and at the Glen Iris Rail Tunnel:

  • delivery of materials
  • adjusting overhead line equipment, signalling, power and communications equipment and cables
  • rail testing and adjusting.

Works within the freight rail corridor and Thornlie Line passenger rail corridor between the Glen Iris Rail Tunnel, Jandakot and Beckenham Street / Dulwich Street, Beckenham include:

  • adjusting track, ballast, sleepers and overhead line equipment
  • installing underground services and drainage
  • building retaining and noise walls
  • installing fencing
  • delivery and unloading of materials.

Upcoming night works in the Mandurah Line rail corridor

Between Glen Iris rail tunnel (south of Roe Highway) and Aubin Grove Station, as well as in and around the Glen Iris rail tunnel and Cockburn Central Station, out-of-hours works are currently planned on the following dates:

  • 16 May
  • 21 May
  • 23 May
  • 26 & 27 May

Existing site compounds, material stockpiles and site access / egress points will be used to support these out-of-hours works, which may result in additional noise during the night. 


Out-of-hours works for rail adjustments - South Lake, Jandakot, Thornlie, and Kenwick

During May and early June, the newly installed rail network will be tested and adjusted between 6pm and 6am nightly. This will involve surveying, tamping and regulating the track, installing Overhead Line Equipment, and using specialised signalling and communications equipment.

This will include: 

  • Night shifts from 15 to 22 May (inclusive)
  • Continuous work (day and night shifts) from 17 May to 19 May and from 4 to 8 June.

Upcoming out-of-hours work - Jandakot, Canning Vale, Thornlie & Kenwick

Across wekeends in May and early June, the team will work at stations and various locations along the new passenger railway between the Glen Iris Rail Tunnel, Jandakot and the rail tunnel between Kenwick and Beckenham.

Key work locations will include:

  • the rail tunnel at Kenwick
  • nearby Kenwick Link and Canning River
  • Spring Road Reserve
  • Thornlie Station
  • Nicholson Road Station
  • nearby Jubaea Court
  • nearby Park Lane 
  • Ranford Road Station
  • nearby Hope Road/Training Place
  • in and around the Glen Iris Rail Tunnel.

Activities will include: 

  • installing and adjusting signalling, communications and power equipment
  • installing and removing fencing
  • excavating for drainage
  • earthworks and asphalting 
  • track adjustments including use of tamping and regulating machines
  • building works at Thornlie Station, Nicholson Road Station and Ranford Road Station
  • earthworks nearby Jubaea Court and Hope/Training Place.

Existing site compounds and site access/egress points will be used to support these out-of-hours works, which may result in additional noise outside of normal hours. 


Building foundations and piers, Jandakot 

There will be work activities in the Glen Iris Drive cul-de-sac alleyway to build foundations and piers for the acoustic gate. This will involve the use of a concrete pump and may require some temporary traffic management in this area of Glen Iris Drive.


Wall construction and painting, Canning Vale and Jandakot

There will be an increase in noise during works to build and paint retaining and noise walls on the south side of the rail corridor between McLean Road in Canning Vale and Lakes Way in Jandakot. 


Rail access construction, Canning Vale

There will be works to build the rail access track and connection points, in the McLean Road verge on the rail corridor side, where McLean Road is parallel to the railway, as well as in the rail corridor between Dowarn Green and Tulloch Way. This will involve excavating, placing and compacting materials, concreting and accessing the site via the local road.

A new rail access point will be built at the end of the Fairfield Gardens cul-de-sac, nearby Fairfield Park and connecting to the Mesa Place cul-de-sac. This will involve installing temporary and permanent fencing and barriers, delivering and moving construction equipment and materials, vegetation clearing where required, excavating, placing and compacting materials. Works take place between 7am and 7pm daily.

A temporary path closure will be in place until end of May to support some rail access construction.

The closure and detour details are below.


Dewatering, Canning Vale and Thornlie

Possible increase in noise from 24/7 use of a pump and generator within the work sites near:

  • Canning River, west of Rimmer Lane, Kenwick
  • Southdown Place, Thornlie
  • O’Dell Street, Thornlie
  • Fairfield Gardens, Canning Vale
  • Nicholson Road Station, Canning Vale

Level crossing permanent closure, Thornlie

The Elliot Place / Cameron Street pedestrian level crossing is permanently closed. Please use the signed detour routes shown in the map below.

The project includes a new footbridge to replace this crossing, providing safer access for pedestrians and cyclists.


Rail access construction and use, Thornlie 

Work will take place to upgrade the existing rail access point between Nyandi Court and the rail corridor. This will then be used to support construction activities in the rail corridor. At times traffic management will be needed on the local road.


Drain and road access construction, Thornlie

Until end-September 2025, there will be works to remove redundant underground services, build a new drain and access road on the north side of the rail corridor near Southdown Place and Corriedale Reserve, Thornlie. This may result in more noise in the area when these works are happening.


Site facility changes and traffic management, Thornlie

The site laydown and parking area on Cameron Street is being extended along the verge and into the road, to support drain and footbridge construction. This involves traffic management on Cameron Street.

The northbound lane of Cameron Street, next to the cul-de-sac, will be temporarily closed until 31 August 2025. Access to properties will be maintained.


Wall construction and painting, Thornlie

There will be an increase in noise during works to build and paint retaining and noise walls on the south side of the rail corridor between Nyandi Court and Kidman Court, and O’Dell Street between Spring Road and Canning River Bridge, and on the north of the rail corridor at the Cameron St cul-de-sac and behind properties on Southdown Place, adjacent to Corriedale Reserve, Thornlie.


Drainage installation and retaining wall work, Thornlie

Until mid-2025, there will be works to upgrade the local drainage network at the Southdown Place cul-de-sac in conjunction with City of Gosnells works to replace a retaining wall and reinstate the local road.

There will be a temporary partial road and path closure with traffic management in place. Access to driveways and properties will be maintained at all times.


Rail access relocation, O'Dell Street, Thornlie

The existing rail access point on O’Dell Street will be relocated further along O’Dell Street, approximately 80 meters south-east.

Works are underway to relocate the access point will include locating underground services, clearing vegetation and concreting.


Reinstatement of O'Dell Street and Spring Road Reserve, Thornlie 

Works are being carried out to reinstate O’Dell Street and Spring Road Reserve which includes reinstating the kerb and path, concreting and revegetation.  


Thornlie Station – Out-of-hours works

Service installation will be carried out during night shift, Monday to Friday from 7pm to 7am, in the Thornlie Station area and to the west of the station carpark, adjacent to Kidman Court, Thornlie.


Canning River path closure, Thornlie

Canning River path under the rail bridges, near O’Dell Street Reserve and Southdown Place/Corridale Place, Thornlie, is closed until mid-2025 with a signed detour in place.


Material movements, Kenwick

There will be an increase in noise and use of Rimmer Lane as the team continues to use and rehabilitate the laydown area between Canning River and Kenwick Link.

Some movements will be needed intermittantly during night shifts.


Rail tunnel upgrade, Kenwick

There will be regular night shifts to support upgrade work inside the tunnel and in the rail corridor near the Thornlie Line rail tunnel, between Kenwick and Beckenham.


Noise wall construction, Kenwick

There will be an increase in noise during works to build and paint a noise wall along Burham Road, in Kenwick. Works will be ongoing until mid-May, Monday to Saturday from 7am to 7pm. 


Site facilities and access points

Out-of-hours works to support and access site at:

  • the bushland south of Berrigan Drive and west of the Kwinana Freeway, via Verna Court, Cockburn
  • Mellor Place, Bibra Lake
  • west of Kwinana Freeway, via Nettle Way, South Lake
  • the corner of Karel Avenue and Berrigan Drive, Jandakot
  • Karel Avenue, west of Orion Road, Jandakot
  • Fairfield Gardens, Canning Vale 
  • McLean Road, Canning Vale 
  • Nicholson Road Station site, Canning Vale
  • Nyandi Court, Thornlie
  • Tom Bateman Reserve on Wilfred Road, and Cameron Street, Thornlie
  • Spencer Road, Thornlie
  • Cameron Street, Thornlie
  • Elliot Place, Thornlie
  • O’Dell Street Reserve and Spring Road Reserve, Thornlie
  • East of Canning River with access via Rimmer Lane, Kenwick
  • Packer Park, Burham Road, Kenwick
  • Albany Highway, near Sydenham Street, Beckenham.

Cockburn Central Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email [email protected] or call 9326 3666. 


Rail infrastructure (ongoing)

Works within the Mandurah Line rail corridor (along Kwinana Freeway) between Roe Highway and Russell Road/Gibbs Road, and at the Glen Iris Rail Tunnel: 

  • delivery and unloading of materials
  • track construction 
  • installing overhead line equipment
  • installing signalling, power and communications equipment and cables
  • rail testing and adjusting.

Upcoming night works in the Mandurah Line rail corridor

Between Glen Iris rail tunnel (south of Roe Highway) and Aubin Grove Station, as well as in and around the Glen Iris rail tunnel and Cockburn Central Station, out-of-hours works are currently planned on the following dates:

  • 16 May
  • 21 May
  • 23 May
  • 26 & 27 May

Traffic management will be required on the Kwinana Freeway in support of some of these works. See Main Roads WA signage and website for details.

Existing site compounds, material stockpiles and site access / egress points will be used to support these out-of-hours works, which may result in additional noise during the night. 

Perth Stadium Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email [email protected] or call 9326 3666. 


Rail Changes

When the Thornlie-Cockburn Link Project is operational, residents in the southern suburbs and along the Mandurah Line will be able to catch a train to Optus Stadium and the Crown Resort at Burswood, without needing to transfer through the Perth CBD. To facilitate this, adjustments need to be made to the rail around Perth Stadium Station.

Service interruptions and traffic management are required to support these essential works, which will impact community members. Please visit the Transperth and Main Roads websites for assistance in journey planning. 


Rail Construction, Burswood

Rail adjustments and installation to accommodate the future Thornlie Cockburn Link services, including installing drainage, and underground services, as well as installing and adjusting track, overhead line equipment, signalling and communications equipment. This will likely result in more vehicular traffic and increase noise levels in the area.

Out-of-hours works are planned, from 7pm to 7am, including public holidays, are planned on the following dates:

  • 19 May
  • 2 June

Traffic management will be required, including on the Victoria Park bridge over rail and Graham Farmer Freeway. See Variable Message Boards and the Main Roads WA website for details.

 

For further information on train and bus services, head to the Transperth website.

Back To Top
OSZAR »